FACILITIES PLANNING PROJECTS

M05541 - Mason Hall HVAC Upgrade
M05537 - Campus Safety Site Lighting Improvements
M05520 - Campus Wide Sidewalk Replacement 
I291ST - Campus Roadway Milling and Paving
051014 - Reconstruct Varsity Drive
051019 - Steele Hall Ice Rink Refrigeration Upgrade
051020 - Replace AHUs & Controls Phase V - Mason Hall 

051018 - McEwen Hall TV Teaching Studio Lighting Rehab
D059HL - McGinnies Hall Roof Replacement

051005 - Campus Energy Metering and Conservation 
051006 - Campus Carbon Monoxide Detection System
051012 - Replace AHUs & Controls Phase IV - McEwen Hall 
301013 - Marvel Theater & Mason Hall Annex Roof Replacement 

05267 - Renovate Houghton Hall (SUCF PROJECT)


Project M05541 - Mason Hall HVAC Upgrade (Fac. Services Project)
Project Phase:  OUT FOR BID
Consultant:  Wendel
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: August 2018
Expected Completion of Construction:  March 2019

LATEST NEWS: Update current through 06/11/2018 -- This project is currently Out for Bid - BIDS DUE 07/10/2018.  

NOTICE TO BIDDERS          Plan Holders List


Project M05537 - Campus Safety Site Lighting Improvements (Fac. Services Project)
Project Phase:  Bid Review
Consultant:  LaBella Associates
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: July 2018
Expected Completion of Construction:  August 2018

LATEST NEWS: Update current through 06/12/2018 -- Bids for this project were received on 6/12/18 - Bid results are listed below. 

BID RESULTS                     Plan Holders List


Project M05520 - Campus Wide Sidewalk Replacement (Fac. Services Project)
Project Phase: Construction Contract Phase
Consultant:  LaBella Associates
Construction Cost: $79,935.00
Contractor:  S. Tabone Construction

Expected Start of Construction: June 2018
Expected Completion of Construction:  August 2018

LATEST NEWS: Update current through 06/11/2018 -- This project is currently in the construction contract phase with the low bidder, S. Tabone Construction.  

BID RESULTS        Plan Holders List


Project I291ST - Campus Roadway Milling & Paving (Fac. Services Project)
Project Phase:  Construction Phase 
Consultant:  LaBella Associates
Construction Cost: $47,420.00
Contractor:  Louis Del Prince & Sons 

Expected Start of Construction: May 2018
Expected Completion of Construction:  June 2018

LATEST NEWS: Update current through 06/11/2018 -- Construction Contract Approved - Construction to begin. 


Project: 051014 - Reconstruction Varsity Drive
Project Phase: Construction Phase  
Design Cost: $45,800.00
Consultant: Nussbaumer & Clarke
Construction Cost: $255,200.00
Contractor: Louis Del Prince & Sons

Expected Start of Construction: May 2018
Expected Completion of Construction: August 2018

LATEST NEWS: Update current through 06/11/2018 -- Construction Contract Approved - Construction to begin. 


Project 051019 - Steele Hall Ice Rink Refrigeration Upgrade
Project Phase:  Design Contract Phase
Design Cost:  To Be Determined
Consultant:  LaBella Associates 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: May 2019
Expected Completion of Construction:  August 2019

LATEST NEWS: Update current through 06/11/2018 -- This project is currently in the design contract phase with LaBella Associates. 


Project 051020 - Replace AHUs & Controls Phase V - Mason Hall
Project Phase:  Design Contract Phase
Design Cost:  To Be Determined
Consultant:  Wendel
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: May 2019
Expected Completion of Construction:  August 2019

LATEST NEWS: Update current through 06/11/2018 -- This project is currently in the design contract phase with Wendel. 


Project: 051018 - McEwen Hall TV Teaching Studio Lighting Rehab
Project Phase:  Design 
Design Cost:  $38,690.59
Consultant:  Popli Design Group 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: December 2018
Expected Completion of Construction: August 2019

LATEST NEWS: Update current through 06/11/2018 -- This project is in the design phase. 


Project D059HL - McGinnies Hall Roof Replacement
Project Phase:  Design
Design Cost:  $65,394.00 
Consultant:  LaBella Associates 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: May 2019
Expected Completion of Construction:  August 2019

LATEST NEWS: Update current through 06/11/2018 -- This project is in the design phase. 


Project: 051005 - Campus Energy Metering and Conservation
Project Phase: Construction    
Design Cost:  $121,916.00
Consultant:  Wendel 
Construction Cost: $495,650.00
Contractor: BECC Electric 

Expected Start of Construction: May 2018 
Expected Completion of Construction:  08/31/2018

LATEST NEWS: Update current through 06/11/2018 -- This project is in CONSTRUCTION.  

 top


Project: 051006 - Campus Carbon Monoxide Detection System
Project Phase: Construction 
Design Cost:  $64,490.00
Consultant:  M/E Engineering 
Construction Cost: $162,220.00
Contractor: BECC Electric 

Expected Start of Construction: December 2017
Expected Completion of Construction:  08/31/2018

LATEST NEWS: Update current through 06/11/2018 -- This project is in CONSTRUCTION. 

top


Project: 051012 - Replace AHUs & Controls Phase IV - McEwen Hall
Project Phase:  Construction
Design Cost:  $267,861.74
Consultant:  Wendel
Construction Cost: $1,400,000.00
Contractor:  MLP Plumbing & Mechanical 

Expected Start of Construction: May 2018
Expected Completion of Construction:  October 2018

LATEST NEWS: Update current through 06/11/2018 -- This project is in CONSTRUCTION.  


Project: 301013 - Marvel Theater & Mason Hall Annex Roof Replacement
Project Phase: Design
Design Cost: $63,926.79
Consultant: Wendel
Construction Cost: To Be Determined
Contractor: To Be Determined

Expected Start of Construction: May 2019
Expected Completion of Construction: August 2019

LATEST NEWS: Update current through 06/11/2018 -- This project is in the design phase.

top


Project: 05267 - Renovate Houghton Hall (SUCF PROJECT) 
Project Phase: Construction 
Consultant:  Mitchell Giurgola
Contractor:  Resetarits Construction

LATEST NEWS: Update current through 06/11/2018 -- Houghton Hall Demo / Abatement and Envelope project - In Construction.

top

Facilities Planning Office

Pleased to provide service Monday - Friday 8:00 am - 4:30 pm
140 Hendrix Hall
State University of New York at Fredonia
Fredonia, NY 14063
(716) 673-3722