Facilities Planning Projects

051004 - Dods Hall Air Conditioning Upgrade
051005 - Campus Energy Metering and Conservation 

051006 - Campus Carbon Monoxide Detection System
M05505 - University Commons Boiler Replacement 
05267 - Renovate Houghton Hall (SUCF PROJECT)
05342 - McEwen Hall Exterior Rehab (SUCF PROJECT)
05344 - Dods Hall Exterior Rehab
05J01 - Replace AHUs & Controls Ph II & Ph II
M05493 - Gregory Hall HVAC Improvements


Project: 051004 - Dods Hall Air Conditioning Upgrade
Project Phase:  Pending Contract Award 
Design Cost: $39,281.00
Consultant:  RAM-TECH Engineers 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction:  5/15/2017
Expected Completion of Construction:  8/11/2017

LATEST NEWS: Update current through 02/08/2017 -- Bids for this project were received on 11/3/16 - See below for results. 

Click here for BID RESULTS

Click here for Current Plan Holders List

top


Project: 051005 - Campus Energy Metering and Conservation
Project Phase:  Design Contract Phase  
Design Cost:  To Be Determined
Consultant:  Wendel 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction:
Expected Completion of Construction:  08/31/2018

LATEST NEWS: Update current through 02/08/2017 -- This project is currently in the contract phase with the selected consultant, Wendel. 

top


Project: 051006 - Campus Carbon Monoxide Detection System
Project Phase:  Design Contract Phase 
Design Cost:  To Be Determined
Consultant:  M/E Engineering 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction:
Expected Completion of Construction:  01/31/2018

LATEST NEWS: Update current through 02/08/2017 -- This project is currently in the contract phase with the selected consultant, M/E Engineering. 

top


M05505 - University Commons Boiler Replacement (Facilities Services Project)

LATEST NEWS: Update current through 02/08/2017 -- This project is currently out for bid with bids due on 2/28/17.  

Click here for CURRENT PLAN HOLDERS LIST 

Click here for NOTICE TO BIDDERS

top


Project: 05267 - Renovate Houghton Hall (SUCF PROJECT) 
Project Phase:  On Hold
Consultant:  Mitchell Giurgola
Contractor:  To Be Determined

LATEST NEWS: Update current through 02/08/2017 -- This SUCF project is currently on hold for reprogramming.

top


Project: 05342 - McEwen Hall Exterior Rehab (SUCF PROJECT)
Project Phase:  Construction 
Consultant:  Bell & Spina
Contractor:  Concept Construction

LATEST NEWS: Update current through 02/08/2017 -- Construction for this summer season is complete and construction will resume again in the Spring of 2017. 

top


Project: 05344 - Dods Hall Exterior Rehab 
Project Phase:  Construction (In Summer 2017)
Design Cost: $126,814.27
Consultant:  Young + Wright Architectural 
Construction Cost:  $851,000
Contractor:  Concept Construction 

Expected Start of Construction:  May 2017
Expected Completion of Construction:  08/11/2017

LATEST NEWS: Update current through 02/08/2017 -- The construction portion of this project has been postponed until the summer 2017 season.

top


Project: 05J01 - Replace AHUs & Controls Ph II & Ph III
Project Phase: Pending Contract Award
Design Cost: $196,150.07
Consultant:  Wendel
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction:  5/15/2017
Expected Completion of Construction:  9/30/2017

LATEST NEWS: Update current through 02/08/2017 -- Bids for this project were received on 2/2/2017 - See below for results. 

Click here for BID RESULTS

Click here for current Plan Holders List 

top


Project No. M05493 - Gregory Hall HVAC Improvements (Facilities Services Project)

LATEST NEWS: Update current through 02/08/2017 -- Bids for this project were received on 1/17/16 - See below for results. 

Click here for BID RESULTS

Facilities Planning Office

140 Hendrix Hall
State University of New York at Fredonia
Fredonia, NY 14063
(716) 673-3722