Facilities Planning Projects

051018 - McEwen Hall TV Teaching Studio Lighting Rehab
McGinnies Hall Roof Replacement (No Project #)

051004 - Dods Hall Air Conditioning Upgrade
051005 - Campus Energy Metering and Conservation 

051006 - Campus Carbon Monoxide Detection System
051012 - Replace AHUs & Controls Phase IV - McEwen Hall 
051014 - Reconstruct Varsity Drive
301013 - Marvel Theater & Mason Hall Annex Roof Replacement 

05267 - Renovate Houghton Hall (SUCF PROJECT)
05342 - McEwen Hall Exterior Rehab (SUCF PROJECT)
05344 - Dods Hall Exterior Rehab
05J01 - Replace AHUs & Controls Ph II & Ph II


Project: 051018 - McEwen Hall TV Teaching Studio Lighting Rehab
Project Phase:  RFQs In Review
Design Cost:  To Be Determined
Consultant:  To Be Determined
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: December 2017
Expected Completion of Construction:  January 2018

LATEST NEWS: Update current through 10/04/2017 -- There were 4 RFQs received for this design project - RFQs are in review. 

Click here for current RFQ Holders List


Project: McGinnies Hall Roof Replacement
Project Phase:  RFQs In Review
Design Cost:  To Be Determined
Consultant:  To Be Determined
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: May 2018
Expected Completion of Construction:  August 2018

LATEST NEWS: Update current through 10/04/2017 -- There were 7 RFQs received for this design project - RFQs are in review. 

Click here for current RFQ Holders List


Project: 051004 - Dods Hall Air Conditioning Upgrade
Project Phase:  Construction Complete   
Design Cost: $39,281.00
Consultant:  RAM-TECH Engineers 
Construction Cost: $194,400.00
Contractor: John W. Danforth Co. 

Expected Start of Construction:  5/15/2017
Expected Completion of Construction:  8/11/2017

LATEST NEWS: Update current through 10/3/2017 -- Construction Complete. 

top


Project: 051005 - Campus Energy Metering and Conservation
Project Phase:   OUT FOR BID   
Design Cost:  $121,916.00
Consultant:  Wendel 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction:
Expected Completion of Construction:  08/31/2018

LATEST NEWS: Update current through 10/16/17 -- This project is currently out for bid - BIDS DUE 11/9/17.

Click here for the Notice to Bidders

Click here for the Current Plan Holders List  

 top


Project: 051006 - Campus Carbon Monoxide Detection System
Project Phase:  OUT FOR BID
Design Cost:  $64,490.00
Consultant:  M/E Engineering 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: December 2017
Expected Completion of Construction:  08/31/2018

LATEST NEWS: Update current through 10/16/17 -- This project is currently out for bid - BIDS DUE 11/2/17.

Click here for the Notice to Bidders

Click here for the Current Plan Holders List  

top


Project: 051012 - Replace AHUs & Controls Phase IV - McEwen Hall
Project Phase:  Design 
Design Cost:  $267,861.74
Consultant:  Wendel
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: May 2018
Expected Completion of Construction:  October 2018

LATEST NEWS: Update current through 10/4/2017 -- This project is currently in design. 


Project: 051014 - Reconstruction Varsity Drive
Project Phase: Design Contract Phase
Design Cost: To Be Determined
Consultant: Nussbaumer & Clarke
Construction Cost: To Be Determined
Contractor: To Be Determined

Expected Start of Construction: May 2018
Expected Completion of Construction: June 2018

LATEST NEWS: Update current through 10/4/2017 -- This project is currently in the design contract phase with Nussbaumer & Clarke. 

top


Project: 301013 - Marvel Theater & Mason Hall Annex Roof Replacement
Project Phase: Design Contract Phase
Design Cost: To Be Determined
Consultant: Wendel
Construction Cost: To Be Determined
Contractor: To Be Determined

Expected Start of Construction: May 2018
Expected Completion of Construction: August 2018

LATEST NEWS: Update current through 10/4/2017 -- This project is currently in the design contract phase with Wendel. 

top


Project: 05267 - Renovate Houghton Hall (SUCF PROJECT) 
Project Phase: Bid Phase 
Consultant:  Mitchell Giurgola
Contractor:  To Be Determined

LATEST NEWS: Update current through 10/04/2017 -- Bids for the Houghton Hall Demo/Abatement and Envelope project were received by SUCF on 10/3/17. The apparent low bidder is Resetarits Construction.

top


Project: 05342 - McEwen Hall Exterior Rehab (SUCF PROJECT)
Project Phase:  Construction 
Consultant:  Bell & Spina
Contractor:  Concept Construction

LATEST NEWS: Update current through 10/4/2017 -- This project is in construction. 

top


Project: 05344 - Dods Hall Exterior Rehab 
Project Phase:  Construction Complete
Design Cost: $126,814.27
Consultant:  Young + Wright Architectural 
Construction Cost:  $851,000
Contractor:  Concept Construction 

Expected Start of Construction:  May 2017
Expected Completion of Construction:  08/11/2017

LATEST NEWS: Update current through 10/4/2017 -- Construction Complete. 

top


Project: 05J01 - Replace AHUs & Controls Ph II & Ph III
Project Phase: Construction Complete 
Design Cost: $196,150.07
Consultant:  Wendel
Construction Cost: $939,700.00
Contractor: MLP Plumbing & Mechanical 

Expected Start of Construction:  5/15/2017
Expected Completion of Construction:  9/30/2017

LATEST NEWS: Update current through 10/4/2017 -- Construction Complete. 

top

Facilities Planning Office

Pleased to provide service Monday - Friday 8:00 am - 4:30 pm
140 Hendrix Hall
State University of New York at Fredonia
Fredonia, NY 14063
(716) 673-3722